ASSEMBLY GUIDE B.P 53 – LES PRAIRIES DE GRAND’VILLE – 44250 SAINT BREVIN LES PINS FRANCE PHONE : 33 (0) 240 391 840 FAX : 33 (0) 240 270 247
Open the catalog to page 1THE seven steps UNLOADING FLOATS ASSEMBLY FRAMES TURNOVER LAUNCHING FRAMES ASSEMBLY GUIDING RINGS AND ACCESSORIES INSTALLATION GANGWAYS INSTALLATION RESULT 2
Open the catalog to page 2UNLOADING DOCKS AND FINGERS FRAMES UNLOADING Docks and fingers are delivered in trucks or containers. To facilitate the docks assembly, three steps are to be followed. More often than not, frames are already turned on the right side, ready to put on the ground for the floats installation. If it is not the case, it is necessary to do this during the unloading process. 1st step : Lifting points. Lifting points have to be balanced on the frame : - docks : place straps over the last crossbars as shown in the diagram below. - fingers : - use the rubber blocks and the extremity ring when placing...
Open the catalog to page 32nd step : Lifting. Once the lifting points are positioned, it is possible to lift the frame with straps. An appropriate crane must be used with sufficient capacity to lift the frames and to carry them the distance to the launching area. Docks and fingers are unloaded the same way. 3rd step : Positioning for insertion of the floats. To go faster, the frames are positioned on the ground upside down. In this configuration, floats can be easily and quickly inserted into the frame. Rubber blocks and fingers connecting pieces will be assembled after the turnover of the frames. 4
Open the catalog to page 4GANGWAY UNLOADING Gangways are unloaded following a specific process: lifting points, lifting, storage. 1st step : Lifting points. Gangways are loaded on the right side, you do not have to turn them over. Lifting points are indicated directly on the upper handrails. As for the frame, the balance is very important. 5
Open the catalog to page 52nd step : Lifting. This is a delicate step as the truck has to move forward while the crane remains still. 1/ The crane lifts the gangway and keeps still 2/ The truck moves forward 1 2 1 2 6
Open the catalog to page 63rd step : Storage. The storage of the gangway is very easy. Next step will be the launching of the gangway with the dock which will receive it. FLOATS UNLOADING AND STORAGE Floats are easier to unload. They are easy to maneuver and stock. When unloading, we recommend classifying the floats by type for easy installation on the frames. A drawing with floats sizes is furnished. 7
Open the catalog to page 7FLOATS ASSEMBLY This is probably one of the most important step of the process. The positioning of the floats is calculated regarding the stability and the floatability required. So the positioning may vary and a layout drawing corresponding to your project is furnished. Standard positioning of the floats for a 40 feet long dock : Standard positioning of the floats for a 23 feet long finger : 8
Open the catalog to page 8Floats are fitted into the extrusion on one side and bolted on the other side on an angle iron. They are maintained with small grooved extrusions, bolts and safety nuts. Fitted into the extrusion Installation methodology is the following : - floats insertion - drilling - bolting 9
Open the catalog to page 91/ Floats insertion. Bolted on an angle iron Fitted into the extrusion 2/ Drilling. 10
Open the catalog to page 103/ Bolting. You are now going to fix the floats on the frame. Once this operation done, the frames can be turned over. 11
Open the catalog to page 11FRAMES TURN OVER When the floats are assembled, the docks are turned over and ready for the launching. The turn over process is as follow : 1/ Lifting points positioning (see 1st step page 3) 2/ Lifting 3/ Storage on the right side LIFTING TURNOVER STORAGE 12
Open the catalog to page 12LAUNCHING Docks, fingers and gangways launching process can be divided in four steps. - straps positioning - lifting - launching - on site transport Straps positioning : Next step is to strap the docks for the launching. A balance placement of the straps is necessary and they must be placed down the frame between the floats. 13
Open the catalog to page 13Lifting : As for the unloading process, the balance positioning of the straps is vital for easy and safe handling. Launching : 14
Open the catalog to page 14On site transport: Once in water, the frame can be transported to its final destination. A small boat is enough for this. We recommend to attach the frame on the side of the boat. DOCKS TRANSPORTATION Accessories are laid down the frame and the cleats are pre-installed. The current should be considered at all times when maneuvering the frames. It is very important to anticipate this element. 15
Open the catalog to page 15FINGERS TRANSPORTATION The fingers which are lighter are transported as shown : GANGWAYS TRANSPORTATION In order to facilitate its installation, the gangway is transported on the same dock on which it will be fastened. As you can see, it is positioned 2/3 on the dock side, 1/3 outside the dock for an easiest handling when operating. 16
Open the catalog to page 16FRAMES ASSEMBLY The frames are joined together using the connecting blocks. These blocks are inserted in gussets welded in the extremity crossbars of the docks. To fasten the blocks, we use vertical bolts length 100mm diameter 16 and security nuts. GUSSET The reinforced rubber blocks and the stainless steel bolts must be greased before insertion. Blocks are used to give to the main dock its elasticity and its strength. We use vertical bolting to avoid any snatching of the extremity crossbars. CONNECTING RUBBER BLOCK The assembly is divided in three parts : 1/ Positioning 2/ Connecting...
Open the catalog to page 171/ Positioning : Docks are turned in their final configuration. 18
Open the catalog to page 182/ Connecting blocks insertion : Once the docks have been positioned, they are assembled. The process continues with the insertion of the rubber blocks in the gussets. To make the insertion of the blocks easier, we recommend the use of a rope attached to two cleats. 19
Open the catalog to page 193/ Bolting : INSERTION OF THE BOLTS 16/100 IN THE BLOCKS : BOLTING WITH THE USE OF A SOCKET WRENCH ON THE TOP: 20
Open the catalog to page 20GUIDING RINGS & ACCESSORIES INSTALLATION GUIDING RINGS’ ASSEMBLY LOADING OF THE GUIDING RING INSTALLATION OF THE GUIDING RING INSERTION OF THE «HAMMER HEAD » BOLTS IN THE SUPERIOR RAIL (diameter 16mm length 40mm, washers diameter 16mm) INSERTION OF THE 4TH RUBBER ROLLER 21